On this morning we finished the last section of 8'x12 floor frame and made sure everything is leveled off. This section will be the computer room.  Wow the black flies are insane. We'll need to do something about this as bug spray is proving ineffective.  Now the building inspector must examine it before we continue.  Rain for the next couple of days. 